Suspension Type 8




Sales Catalog, Suspension pages
(pdf 0.4 mb)





Step by Step
Installation of Type 8


Before Starting the Installation

* Unpack all the components and place
them on a clean surface (mat/sheet).
Check to make sure that you have recieved
all the components specified on the enclosed
parts list. If components are missing,
contact FabricAir, Inc. immediately.

* In order to keep the FabricAir ducts clean,
handle the ducts with clean hands. Make
sure that any tools which might come in
contact with the ducts have been cleaned
before use.

* Make sure that the necessary tools are
available - see the instructions.

* Provide hardware for anchoring - see items
1 & 3 under installation sequence.

* If the ducts are to be installed in a new
building, purge the handling systems and
install the prefilter before installing the
FabricAir ducts. This is done to remove
dust, which would otherwise collect in
the FabricAir duct.

Installation Sequence

1. Install anchors, centered above the duct,
with the appropriate distances shown in
the drawing. The anchors are not included
in the shipment, as the type of anchor
depends on the building structure. Fasten
the anchors directly to the overhead surface.

2. Cut the cable (13) into suitable lengths,
depending on the distance between the
overhead and the top of the rail.

3. Install the cable (13) into the eyelet for
the H-rail (7).

4. Install H-rail (21) by attaching to the
eyelet for the H-rail (7).

5. Join rails together using joiners (6).

6. Once the rail has been installed, install
the FabricAir duct. If the duct is shorter
than 30', it will normally be delivered in
one section. If the duct exceeds 30' it will
normally be divided in sections with zippers.
Put the gliders of the duct into the rail. If
the duct is divided in sections - begin with
the first section.

7. When all sections are installed in
the rail, zip the sections together.
Fasten the duct to the hem connection
on the AHU collar with the mounting
belt (17/18), and install the end cap
for H-rail (8).

Follow the above procedure for installing
FabricAir Plenum ducts. Zip the FabricAir ducts
to the FabricAir Plenum duct.


After Completing the Installation:

Always be sure to give the customer a
copy of the maintenance instructions
and information concerning mainte-
nance intervals.